Jump to content



  • Please log in to reply
No replies to this topic

#1 GD1123


    New Member

  • Members
  • Pip
  • 1 posts

Posted 01 July 2014 - 06:09 PM

23. A project manager is running into trouble with his team, because they always come to
meetings late. Which of the following is MOST LIKELY to be the cause of this problem?
A. The team resents the work that they’re doing.
B. The project manager needs to schedule meetings later in the day.
C. The project manager was late to meetings himself, and this influenced the team.
D. The team is in the storming phase of team development.

The correct answer is C as per Headfirst practice questions. But i did not understand why. Why not the 1st Option?

0 user(s) are reading this topic

0 members, 0 guests, 0 anonymous users