The following PMP® exam sample question is taken from the Free PMP Exam Simulator (The answer is at the very bottom):

------------------------------

You are managing a software development project. In the middle of the project, you find out that you are way behind schedule. Your company has invested a lot in this project, and if you don't deliver the project on time, it will be a total disaster. You analyze your project schedule to adjust it so that you may be able to complete the project on time with the existing resources. You find out that you have a lot of discretionary dependencies in your project schedule. What is the best way for you to adjust the project schedule so that you may be able to complete the project on time?

A) Keep the discretionary dependencies intact and apply Crashing
B) Keep the discretionary dependencies intact and apply Fast Tracking
C) Remove the discretionary dependencies and apply Crashing
D) Remove the discretionary dependencies and apply Fast Tracking

------------------------------

Hint: You need to find a way out of this problem with your existing resources.

------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Until Next Time,
Cornelius Fichtner, PMP
President, OSP International LLC
https://www.project-...nt-prepcast.com

Answer and Explanation:
The Correct Answer is D. As you need to find a way out of this problem with your existing resources, you can't apply the Crashing technique. You can only apply Fast Tracking after removing the discretionary dependencies from the project.
0

#2 User is offline   Poonam23 

  • Active Member
  • PipPip
  • Group: Members
  • Posts: 11
  • Joined: 09-October 14

Posted 23 October 2014 - 09:10 PM

You can get few more PMP exam sample questions Here
0

Share this topic:


Page 1 of 1
  • You cannot start a new topic
  • You cannot reply to this topic

1 User(s) are reading this topic
0 members, 1 guests, 0 anonymous users