You are performing Earned Value Management on your project. The Cost Performance Baseline in Earned Value Management is also a part of:
A.) Cost Estimating Baseline
B.) Performance Measurement Baseline
C.) Cost Measurement Baseline
D.) Budget Baseline
------------------------------