Hello all,
Here are some interesting questions I've found after taking an online test; would really appreciate if you could give me your opinion on them
40. You are a project manager on a large technology project and have noticed the project team can't easily find the
right information to make good decisions and there is a lot of confusion about which versions of documents are
the most up-to-date. You are also having a tough time integrating the various processes. As a result you suggest
improvements be made to which of the following?
a. Project Management Information Systems (PMIS)
b. Work Breakdown structure (WBS)
c. Configuration management systems
d. Reporting systems
--> correct answer a but I think it's C because there is where all the updated and different versions of the documents are hence all the most updated versions
Then why is A correct over C?
118.The team is working on creating a project team directory. Which process is the team most likely engaged in?
a. Resource planning
b. Organizational planning
c. Staff acquisition
d. Information distribution
--> correct answer C; but I don't understand why; what do you think?
198.What is a Pareto diagram?
a. A plot of results over time
b. A histogram showing frequency of occurrence and category of an identified cause
c. A plot of group average and groups
d. A histogram, frequency of occurrence and range
--> correct answer B but why? A histogram involves a time dimension and the Pareto chart only has the frequencies and the categories; what do you think?
Screen clipping taken: 1/4/2013, 12:35 PM
i. What is the difference between work performance measurements and work performance information
ii. What is the difference between Activity Code and Activity Indetifier
iii. What is the difference between Scope Verification, Scope Control and Quality Control?
iv. What is the difference between communication methods and communication models?