Posted 06 November 2012 - 06:45 AM

The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

Your pharmaceutical drug manufacturing project is running late and you have deadlines to meet on your project. You want to replace some of the inefficient human resources with more talented human resources to finish the project on time. What risk response strategy is being followed in this context?

A.) Share
B.) Accept
C.) Transfer
D.) Mitigate

------------------------------
Hint: You are trying to reduce the likelihood of the risk occurrence.
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Please click here for the correct answer and explanation.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC - http://www.project-m...nt-prepcast.com