------------------------------
Joe is working as a project manager in a highway construction project. He wants to use a fixed price contract instead of cost-plus contract. The risk response strategy he is using in this case is an example of?
A) Risk Avoidance
C) Risk Mitigation
D) Risk Acceptance
-----------------------------
Hint: The project manager in this example is currently performing the Conduct Procurements process but the answer is in the Plan Risk Responses process.
------------------------------
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ - http://www.project-m...nt-prepcast.com
The Project Management Podcast™ - http://www.project-m...ent-podcast.com
ANSWER AND EXPLANATION:
The correct answer is B
Explanation: Risk Transference requires shifting some or all of the negative impact of a threat, along with the ownership of the response. A fixed price contract may transfer risk to the seller, whereas a cost-plus contract may transfer cost risk to the buyer.
Reference: PMBOK Guide 4th Edition, page 304
This post has been edited by Cornelius Fichtner: 13 June 2012 - 02:45 AM












