On your project you handle known risks by performing the Plan Risk Responses process. Which of the following would you use when you encounter unknown risks?

A.) Risk Reserves
B.) Risk Mitigation
C.) Risk Transfer
D.) Risk Acceptance

Hint: Unknown risks cannot be managed proactively.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ - http://www.project-m...nt-prepcast.com
The Project Management Podcast™ - http://www.project-m...ent-podcast.com

The correct answer is A
Explanation: Unknown risks are handled by applying Risk Reserves in the project.
Reference: PMBOK Guide 4th Edition, pages 304, 311