O'Reilly Forums: A Question About Pert Calculation.please Help Calculate And Explain It.thank You In Advance! - O'Reilly Forums

Jump to content

Page 1 of 1
  • You cannot start a new topic
  • You cannot reply to this topic

A Question About Pert Calculation.please Help Calculate And Explain It.thank You In Advance! PERT calculation

#1 User is offline   Jason_sfh 

  • New Member
  • Pip
  • Group: Members
  • Posts: 1
  • Joined: 07-February 12

Posted 07 February 2012 - 07:06 PM

Together with your team, you applied three-point estimation on a Critical path which consists of two activities.

The following duration uncertainties are all calculated assuming a ±3sigma Confidence interval.

The duration uncertainty-defined as pessimistic minus optimistic estimate-of the first activity is 18 days; the second estimate has an uncertainty of 24 days.Applying the PERT formula for paths, what is the duration uncertainty of the entire path?

[A] 21 days
[B] 30 days
[C] 42 days
[D] No statement is possible from the information given.

This post has been edited by Jason_sfh: 07 February 2012 - 07:07 PM

0

#2 User is offline   raulcid 

  • New Member
  • Pip
  • Group: Members
  • Posts: 7
  • Joined: 05-February 12

Posted 18 March 2012 - 06:27 PM

The correct answer, in my view, is B: 30 days. This the way I would solve the problem:

1. Calculate sigma, the standard deviation, for each activity using the PERT formula

sigma= (pessimistic - optimistic) over 6.

We get a sigma of 3 for the first activity, and a sigma of 4 for the second activity.

2. Calculate the variance for each activity using the formula

variance = sigma^2

We obtain a variance of 9 for the first activity, and a variance of 16 for the second activity

3. Add the variances of the two activities to obtain the total variance in the critical path.

We get a total variance of 9+16 = 25

4. Take the square root of the total variance in order to obtain sigma for the project

sigma for the project = square root of 25 = 5

5. Calculate the duration uncertainty of the entire path assuming a plus minus 3 sigma interval, that is an interval of 6 sigma.

We get confidence interval for the entire project = 6 x 5 = 30.
0

#3 User is offline   Deep Fried Brain 

  • Active Member
  • PipPipPip
  • Group: Members
  • Posts: 99
  • Joined: 13-March 09

Posted 01 April 2012 - 06:43 PM

Raul,

Your calculations look correct to me. Interesting question.

Best regards.
BrainBOK = ITTOs + Quizzes + Exams + Flashcards
-------------------------------------------------------------------
http://www.brainbok.com
http://www.deepfriedbrainproject.com
-------------------------------------------------------------------
0

Share this topic:


Page 1 of 1
  • You cannot start a new topic
  • You cannot reply to this topic

1 User(s) are reading this topic
0 members, 1 guests, 0 anonymous users