A. Cost estimating.
B. Scheduling
C. Cost budgeting.
D. Communications planning.
I came across this question on one of the free test sites. My guesss was C. But as per the test result the answer is B.
Explaination is
Scheduling will have to be done again if funds are not scheduled to be available in time to meet the pre-existing schedule. New constraints, such as start no earlier than, will be imposed on some activities. PMBOK 7.2.2.1, p. 169
I referred to PMBOK 7.2.2.1 section but it does not have any conclusive referrence.
Can you please explain